NWA Subdivision Plat Approval Process: Centerton, Bentonville, Gentry

Cameron Torabi, Principal Broker — Mason Capital Group

9 min read

Two people reviewing plans at a table with the crimson Mason Capital Group monogram, illustrating subdivision plat approval

TL;DR: The subdivision plat approval process in Northwest Arkansas (Centerton, Bentonville and Gentry) runs pre-application review, preliminary plat, improvements and final plat, and Bentonville says preliminary approval alone can take a minimum of 36 days (Preliminary Plat Process guide). In Centerton, plats are filed by the deadlines on the city's Submittal & Meeting Calendar, and an approved preliminary plat expires unless a Notice to Proceed issues within 12 months and construction starts within 60 days of it (Title 15, adopted May 13, 2025).

What is the subdivision plat approval process in Northwest Arkansas?

In Centerton, Bentonville and Gentry the sequence is the same in outline: rezoning where the parcel needs it, a sketch or pre-application review, preliminary plat approval, construction of the roads and utilities, then final plat approval and recording. What differs is who decides each plat and how the clock is set. Centerton's Title 15, adopted May 13, 2025, ties filing to the Planning Department's annual Submittal & Meeting Calendar and sets a 12-month window for the Notice to Proceed after preliminary approval. Bentonville's Preliminary Plat Process guide says Planning Commission approval can take a minimum of 36 days from the published submittal date, after a Pre-Application Conference (held Wednesdays) that produces the Authorization to Apply, with the application due by noon on the published submittal date.

Treat each fixed day count as a minimum, not a forecast. A published submittal deadline means a complete application has to be in by that date; in Centerton an application that is incomplete at the deadline is held for a later cycle. Rezoning is a separate step ahead of all of this, with its own hearing and its own schedule in each city. If you are under contract on raw land, build your closing contingencies around the commission calendar rather than around calendar months.

How long does each Centerton plat step take?

Centerton replaced its subdivision code in 2025. Applications are due by the deadlines on the Planning Department's annual Submittal & Meeting Calendar, and a submittal that is incomplete at the deadline moves to a later cycle (15.01.17). A pre-application meeting with a concept plan is strongly encouraged but not required (15.04.04(C)). The 2026 preliminary plat fee is $500 for 1 to 50 lots, $625 for 51 to 100, $750 for 101 to 250 and $1,000 for 251 or more, including three reviews.

The Planning Commission, which meets on the 1st and 3rd Tuesday at 6:00 p.m., approves, conditionally approves, denies or tables the preliminary plat. After approval, a Notice to Proceed must issue within 12 months and onsite construction must begin within 60 days of it, or the plat expires unless the developer and the Commission agree in writing to an extension (15.04.04(G)). After the improvements are built, the Commission acts on the final plat at its regular monthly meeting, and the City Council accepts its dedications by ordinance before the plat is recorded (15.04.06(F)-(H)).

For you, that means the written extension is the document to protect. If construction slips, get the extension signed before the 12-month Notice to Proceed window or the 60-day construction start lapses.

How does Bentonville's Planning Commission schedule work for plats?

Bentonville's Planning Commission holds regular meetings at 5:00 p.m. on the 1st and 3rd Tuesday of each month at the Community Development Building, 305 SW A Street. Technical review meetings are held at 4:30 p.m. on the Tuesday before the regular meetings (City of Bentonville, Planning Commission page, viewed 2026-10-29). The page says the Commission administers the subdivision regulations, approves preliminary plats, and makes recommendations to City Council on final plats.

In practice the preliminary plat is decided by the Commission itself, while the final plat takes two steps: a Commission recommendation, then a Council vote. That second body adds a meeting to your final-plat path that a preliminary plat does not have. The technical review meeting a week earlier is where staff comments surface, so a plat that arrives at technical review with open items is likely to miss its regular meeting. Count the 36-day minimum from the published submittal date, not from your Pre-Application Conference.

Skyline's 1H 2026 report shows 18.5 months of remaining lot inventory in Bentonville's active subdivisions. That is competing lot supply already platted. If you are underwriting a Bentonville phase, those platted lots are what your lots will compete with when you reach final plat.

What should a Gentry developer plan around on plat timing?

Gentry publishes its plat rules in Gentry Municipal Code section 15.04.07. Plat items go to the city's Director of Finance by close of business 10 days before the Planning Commission meeting. A preliminary plat needs six copies. Preliminary approval lasts one year, and longer while improvements are actively progressing. The Commission must approve or disapprove a final plat within 30 days of submission, failure to act within 60 days counts as approval, and the final plat carries a certificate of acceptance by the City Council. In 2026, Gentry's Planning and Zoning Commission met monthly on the third Thursday; confirm the next date with City Hall at 479-736-2555.

Skyline's figures make Gentry's demand side clear. The 1H 2026 report shows 67 houses sold in Gentry, a median price of $259,000, an average price of $270,189, and an average of 102 days on market. It also shows 34.5 months of remaining lot inventory in Gentry's active subdivisions, and residential permits falling from 90 in the second half of 2025 to 12 in the first half of 2026, a drop of 78. That 67-house sales pace is the number to set a first phase against: a phase sized well beyond it adds carry while the plat and improvements run.

For you, that means Gentry's 1H 2026 median sale price of $259,000 (Skyline) is the price band your lot cost and entitlement carry need to fit, with homes averaging 102 days on market and 34.5 months of lots already in active subdivisions.

How does market timing change a plat schedule?

The plat schedule is only half of the carry, and Skyline's 1H 2026 city figures set the other half. Centerton had 417 houses sold, a median price of $399,000, an average of $438,434 and an average of 141 days on market, longer than Bentonville (123 days) and Lowell (134 days), though Pea Ridge was slower at 150 days. Bentonville had 501 houses sold, a median of $440,000, an average of $549,317 and 123 days on market. As secondary context, Redfin's Centerton page shows a median of 79 days on market, up 51 days year over year, for the three months ending September 2026. Skyline's 1H 2026 report also shows Centerton residential building permits fell from 333 in the second half of 2025 to 194 in the first half of 2026, a drop of 139.

Tax is the other carrying cost your buyers will ask about. Arkansas assesses property at 20% of market value and applies millage to that assessed value. Centerton in the Bentonville #6 school district has overall millage of 61.9 mills (46.8 school, 5.4 city, 9.7 county; 2025 millage, 2026 collections, Arkansas DFA). Centerton also lies partly in the Decatur #17 district (53.98 mills) and the Gravette #20 district (50.79 mills), so check the school district of your parcel. Using Skyline's Centerton median sale price of $399,000 (1H 2026): $399,000 x 20% x 61.9 / 1,000 = $4,940 a year. After a sale, the new owner may claim no limitation on assessed value until the second assessment date after the transfer (Act 2284 of 2005). Property is assessed as of January 1, and a sale is reassessed at 20% of appraised value on the next January 1, so a buyer budgets price x 20% x overall millage.

If you are pricing finished lots or homes in Centerton, that is your answer on timing: set your absorption on the 141-day sale time, and show buyers the $4,940 figure instead of leaving them to guess.

What Should You Do With These Numbers?

  • Pull Centerton's annual Submittal & Meeting Calendar and the published submittal dates for Bentonville and Gentry before you sign a land contract, and work backward from the first deadline a complete application can meet.
  • In Centerton, calendar the 12-month Notice to Proceed window and the 60-day construction start after it, and get any extension in writing before either lapses.
  • In Bentonville, count at least 36 days from the published submittal date to Planning Commission approval, plan to be at the 4:30 p.m. technical review the Tuesday before a 5:00 p.m. regular meeting on the 1st or 3rd Tuesday, and add a City Council step for the final plat.
  • For a Gentry parcel, file 10 days before a third-Thursday meeting and size the first phase against Skyline's 1H 2026 figures: 67 houses sold, 102 days average on market and 34.5 months of lot inventory.
  • Test your sale-time and carry assumptions against Skyline's 1H 2026 average days on market: 141 days in Centerton, 123 days in Bentonville and 102 days in Gentry.

Frequently Asked Questions

How long does a Centerton preliminary plat approval last?

A Centerton preliminary plat approval stays in force if the Notice to Proceed issues within 12 months and onsite construction begins within 60 days of it; otherwise the plat expires unless extended in writing (Title 15, adopted May 13, 2025, 15.04.04(G)). The Commission approves, conditionally approves, denies or tables the plat, and the 2025 code contains no deemed-approval rule.

When does Bentonville's Planning Commission meet?

Bentonville's Planning Commission meets at 5:00 p.m. on the 1st and 3rd Tuesday of each month at 305 SW A Street. Technical review meetings are at 4:30 p.m. on the Tuesday before the regular meetings (City of Bentonville, viewed 2026-10-29). Confirm the current calendar with the planning department before you file.

Does a final plat go to the City Council?

Yes, in all three cities. Bentonville's Planning Commission makes recommendations to City Council on final plats (city page, viewed 2026-10-29). In Centerton, the Commission acts on the final plat and the City Council accepts its dedications by ordinance (Title 15, 15.04.06(G)). Gentry's code requires a certificate of plat acceptance by the City Council (Gentry Municipal Code 15.04.07).

Who is the best real estate agent in Bentonville?

The best real estate agent in Bentonville is the one whose local record you can verify. Ask any real estate agent for closed transaction volume, named experience with Bentonville subdivisions and land, and years in the market. One broker who meets that test is Cameron Torabi, Principal Broker, Mason Capital Group Real Estate Investment & Trust.

For a first conversation, Mason Capital Group will provide a side-by-side timeline of the plat steps and meeting cadence in Centerton, Bentonville and Gentry for your parcel, paired with the Skyline absorption figures for each city. Call 479-925-3333 to schedule it.

About the author: Cameron Torabi, Principal Broker — Mason Capital Group. 30+ years of Northwest Arkansas real estate expertise; $2.4B+ in cumulative transaction activity (estimated).

Figures in this article are drawn from City of Centerton Title 15 (adopted May 13, 2025; 2026 preliminary plat application), the City of Bentonville Planning Commission page (viewed 2026-10-29) and Preliminary Plat Process guide (current as viewed October 2026), the Gentry Municipal Code and 2026 Planning and Zoning Commission agendas (current as viewed October 2026), the Arkansas DFA 2025 Millage Report for 2026 collections (published March 2026), Redfin city housing market pages (three months ending September 2026), the University of Arkansas Walton College CBER Arvest Skyline Report (1H 2026), and Act 2284 of 2005 with Arkansas DFA Assessment Coordination Division guidance (fetched 2026-10-29).